Early Warning Signals for a BPI Project and What to Do about Them

Can you recognize the early warning signals that derail a business process improvement project? Many articles have been written about what makes process improvement projects fail and usually they list critical success factors. But the real question is how do you recognize the leading indicators in a process? And once you identify these signals what action should you take to cure the ill and get the process back on track or put a halt to the project altogether?

Let's look at the stages of the BPM Methodology and identify early warning signals and then suggest some countermeasures that are helpful to get things righted again.

BPM Process Methodology

This graphic shows the four stages of the BPM Methodology and the detailed phases of stage 2, the Business Process Improvement Project.

The first early warning signal is in stage 1, Process Selection, or choosing which process to work on. It's not that there is one right process to work on first but the choice of a poor project creates many challenges that often lead to a bad name for the whole concept of business process management. The wrong process choice is usually from three circumstances:

  1. Starting with an enterprise project with several cross-functional stakeholder groups participating.
  2. Choosing a project where a single Executive Sponsor cannot be designated and it needs two to three Process Owners
  3. Starting with a project that requires a different culture than the organization currently has. This would be the case if the culture was authoritarian and it tried to use employee process improvement teams.

The answer to these warning signals is don't start with a large enterprise process projects without the necessary leaders, and a culture to support it. Instead start smaller, with a key sub process, with leadership and a culture in that function or business unit that support employees working together and understanding how to look at a process and use data, diagrams, and the voice of the customer to improve it.

In the Chartering and Staffing phase of the BPI project there are many critical success factors (It is the beginning of the project! Get it right and you are off to a good start, but get it wrong and you'll create numerous problem areas). Let me discuss two factors:

The Project Charter
Below are four early warning signals that can come up during the charter process.

(See my book, The BPI Blueprint: A Step-By-Step Guide to Make Your Business Process Improvement Projects Simple, Structured, and Successful, for a charter template, completed charter example from a client, and details on how to create one.)

  1. Having no charter. Maybe this happens because the BPM professional staff or IT knows this process needs working on and just begins. There is no written charter, and minimal involvement of the business executives in defining the improvement goals.
  2. No baseline measures. Without baseline measures, there is no quantitative data to see how critical this problem is, as well as data to see what the current situation is and what kind of goal value should be set for the improvement
  3. Uncommitted leadership. There is no Process Owner who is designated and steps up to guide this effort, setting the goals, vision, measures, scope, and selecting and providing the necessary team resources. Or the Process Owner has limited time for the team and moves onto other initiatives.
  4. Overburdened team members. Several team members says they have too many other projects and will not be able to devote time to this additional BPI project.

What can you do in these situations?

  1. If there is no charter, stop and develop one. Go back and do it. Write it down, put it in the Shared Repository and keep using it and iterating it as the project moves along. If the company has a real anathema to charters, don't call it a charter, but gather the elements, and name the file something else, or put it in Blueworks Live in the appropriate fields as part of the project overall.
  2. Once you have the improvement goals for the project they will need measures. So name the appropriate measurement categories and then gather the real baseline data. It doesn't have to be for the past three years; make it simple. But it may take some manual work this first time because process measures are not automated in most companies today.
  3. If you have uncommitted leadership, stop. Get different leadership, but make sure they have the responsibility for the process. Or, pick a different process where there is the appropriate Process Owner with commitment to the BPI project. Uncommitted leadership is a big stumbling block –not worth investing in.
  4. Overburdened team members is usually a sign of a larger problem—the company has too many priorities and keeps adding more assignments without taking some items off the plate. Team members can be 'conscripted' to join the team, but if they really do not have time to work on the BPI they will soon start voting with their feet and just not coming to working sessions. So reconsider if this is the right process at this time. Maybe another process where the employees are not so stretched would be better. If just one or two team members are overburdened, it may be possible to find good alternates, but if there are several, don't start this BPI project.

Phase 2, 3, and 4 of the BPI Project are about doing the modeling, analyzing and redesigning the process. There are individual red flags within each phase, and another blog will address them later. But the biggest one I see is if the project drags on too long. How do you recognize this early?

  1. There is no project plan with dates for all meetings scheduled from start to finish. Instead meetings are scheduled one by one.
  2. Meetings keep getting postponed.
  3. Meetings with the Process Owner are delayed and cause delays in the BPI teamwork.

Here's an easy tip. Look for this pattern and speak about it quickly. And I say a pattern is any combination of three of these items or three repeats of any of these items. Then discuss the project with the Process Owner, determine root cause, and be prepared to re-energize the team. Do one of the following (1) set a new time-boxed schedule, (2) take a break and restart later (which will be very difficult), or (3) fold the team.

These are important leading indicators that the process is in trouble. Take the early warning signals as valid information and be ready to have a discussion with the appropriate players and take action. Otherwise your BPI project could drag on, probably getting weaker, and not moving toward success.

SweetCover V5 thumbMy new book, The BPI Blueprint: A Step-By-Step Guide to Making your Business Process Improvement Projects Simple, Structured, and Successful, was just published in February and is now available on Amazon.com

Nathaniel Palmer
Author: Nathaniel PalmerWebsite: http://bpm.com
VP and CTO
Rated as the #1 Most Influential Thought Leader in Business Process Management (BPM) by independent research, Nathaniel Palmer is recognized as one of the early originators of BPM, and has led the design for some of the industry’s largest-scale and most complex projects involving investments of $200 Million or more. Today he is the Editor-in-Chief of BPM.com, as well as the Executive Director of the Workflow Management Coalition, as well as VP and CTO of BPM, Inc. Previously he had been the BPM Practice Director of SRA International, and prior to that Director, Business Consulting for Perot Systems Corp, as well as spent over a decade with Delphi Group serving as VP and CTO. He frequently tops the lists of the most recognized names in his field, and was the first individual named as Laureate in Workflow. Nathaniel has authored or co-authored a dozen books on process innovation and business transformation, including “Intelligent BPM” (2013), “How Knowledge Workers Get Things Done” (2012), “Social BPM” (2011), “Mastering the Unpredictable” (2008) which reached #2 on the Amazon.com Best Seller’s List, “Excellence in Practice” (2007), “Encyclopedia of Database Systems” (2007) and “The X-Economy” (2001). He has been featured in numerous media ranging from Fortune to The New York Times to National Public Radio. Nathaniel holds a DISCO Secret Clearance as well as a Position of Trust with in the U.S. federal government.